When we look at the LinkedIn posts, we see many post about sophisticated concepts and techniques which seems majority of the projects around the world are utilizing these concepts and as the result they get delivered successfully!
However, our experience demonstrates the opposite scenario where the vast majority of the Projects are stuck in basics and failure owing to the lack of effective implementation despite many using CONSULTANTS! We have had many posts as regards utilization of Duration% complete, Dummy Resource, etc. to illustrates that Projects are failing in the BASIC concepts. Here are 3 cases we witnessed recentlys:
Case 1: The Dummy Resource Trap
A contractor used a Dummy Resource and reported 72% progress based on Duration. Our investigation found the actual progress was only 56%.
Case 2: Misaligned Metrics
The project reported being 6% behind (39% actual vs 45% plan). In reality, the progress was only 25% based on P6 Earned Budgeted Units.
Case 3: The Risk Analysis Paradox
A consultant performed a Schedule Risk Analysis (SRA) for a 28-month project. The P70 date showed only a 4-month delay.
Progress reports, S-Curves, and resource loading are basic concepts that MUST be correct. Don't be surprised by high failure rates when the foundations are built on noise.