Resource Management

Budgeted Units vs. No. of Resources

Published 08 November 2020

The Schedule development is a complex process which requires many data, calculations, skills and knowledge. Even, if the data is available, most of the Planners fail to develop it accurately. Some Planners try to come up with a sensible solution but when they get checked in detail, many inaccuracies are discovered. We did discuss one of them (assigning direct resources to LOE or WBS summary) in another article. In this article, we will discuss another practice which seems widely used and accepted as a correct process.

To demonstrate the practice, we will use the following activities:

Baseline Activities for demonstration

Step 1: Masking the Units

The confusion usually begins with the User Preferences. A planner sets the Units Format to "Day" and uncheck "Show Unit Label." This hides whether P6 is looking at hours or days, creating the perfect environment for an incorrect resource loading output.

P6 User Preferences - Unit Format set to Day

Step 2: The "Headcount" Assignment

Once the resource pool is created, the planner begins assigning resources to each activity. For example, for Activity A1670, he.she assigns a Civil Engineer, a Mechanical Engineer, and two Designers. The planner then defines the required number of resources: one Civil Engineer (budgeted unit = 1), one Mechanical Engineer (budgeted unit = 1), and two Designers (budgeted units = 2). This same approach gets applied to the rest of the activities in the schedule. The results will be the same as the table below:

Assigning resources based on headcount

In the schedule, the loading looks visually "clean" because the labels are hidden:

Schedule view with hidden unit labels

Extending the same practice to the Construction

The same process is applied to construction activities. The planner assigns a specific number of Labors and Non-Labors, assuming that entering "3" or "4" represents the number of resources per activity.

Construction resource assignment table

The schedule results appear to follow the plan perfectly:

Resulting construction schedule

The Reveal: The Mathematical Collapse

Everything looks correct, until you switch the Units Format back to "Hour" and tick "Show Unit Label."

Switching preferences back to Hours

Now, P6 exposes the reality of the budgeted units. For a construction activity spanning 25 days to build a 30m³ foundation, the schedule now indicates it only requires 24 total man-hours (8 hrs/day × 3 resources).

The broken math revealed in hours

The Bottom Line

Budgeted Units are not a headcount. They represent the total man-hours required to complete the activity's scope of work.

In a real-world project with hundreds of activities, it is virtually impossible to identify exactly how many laborers will be on a specific task every day and then ask the project team to assign the same number of resources to activities (what is the solution?). By confusing headcount with man-hours, you create a schedule that is mathematically impossible to execute.

Master the Mechanics of Resource Loading

Don't let display settings hide flawed logic. Learn the correct methodologies for Resource Loading and Schedule Development through our expert-led training courses.

Join Our Training Programs

Discussion

AB
Abdijabar sheik
28 Feb 2022

I like project planning in engineering

Leave a Comment